Construction Update—January 2007
January 10th, 2007Methodist Boerne is on its way towards completion! Landscaping around the property as well as stucco work, roofing and wall covering will continue into next week. Asphalt for parking lot is set and ready. Millwork and tiling have been completed in the Lobby and restrooms.
Work Completed This Period
- Continue stucco
- Complete millwork at lobby
- Restroom complete
- Tile at lobby complete
- Continue landscaping
- Asphalt complete
Work Scheduled for Next Period
- Complete stucco
- Complete paint and wall covering
- Complete landscaping
- Complete roofing